Goldman Plumbing was contracted to upgrade one of Blacktown Hospitals warm water systems. The existing system was at end of life and had failed. Goldman Plumbing established a temporary warm water supply from an adjacent system to meet the Hospitals operational requirements.
The failed heat exchange system was drained, dismantled and removed from site.
Goldman Plumbing’s Engineers designed an alternate system consisting of 4 x Aleabrax GFX 180 storage heat exchangers to replace the failed LEX warm water heat exchanger.
Goldman Plumbing’s Technicians modified the existing pipework to suit the new warm water systems configuration. Thermal insulation and metal sheathing was added to the new pipework to match the existing.